DPS statement on Blenheim Rd.: Thank you for contacting us about the status of the Blenheim Road resurfacing project from High Street to Indianola Avenue. The City of Columbus makes critical investments in street resurfacing projects like Blenheim to improve the quality of our roadways and infrastructure that residents depend on every day.
Relocation of the main gas line on Blenheim by Columbia Gas must be completed before the city rebuilds and paves the street so the utility construction doesn’t tear up a newly resurfaced street. Delays in Columbia Gas completing the main gas line relocation have pushed the Blenheim resurfacing project to next spring. Columbia Gas will be working on the relocation this fall and winter.
DPS update on Glencoe Rd with timeline attached